1. Market dynamics have changed. The project sponsor wants to terminate the project because of its uncertain performance. What should the project manager and the project sponsor review?

市場動態發生變化。由于項目績效不確定,項目發起人希望終止項目。項目經理和項目發起

人應審查什么?

A. A root cause analysis and an action plan for the technical issues

根本原因分析和技術問題的行動計劃

B. Project's technical and commercial goals, viability, and profitability

項目的技術和商務目標,可行性和盈利性

C. A change request to modify the project requirements

修訂項目需求的變更請求

D. Explanations of the processes that caused the technical issues

對導致技術問題的過程進行解釋

 

2. What is the main objective of the Executing Process group?

執行過程組的主要目標是什么?

A. Tracking and reviewing the progress of the project

跟蹤并審查項目進度

B. Managing stakeholder expectations

管理利害關系者的期望

C. Satisfying the project specifications

滿足項目規范

D. Monitoring the schedule

監控進度表

 

3. Which of the following statements reflect the degree of risk to the project?

下列哪項陳述反映了項目的風險程度?

A. Risk is greatest at the beginning of the project.

項目初始階段的風險最大。

B. Risk is least at the beginning of the project.

項目初始階段的風險最小。

C. Risk is constant throughout the project.

風險在整個項目期間保持恒定。

D. Risk is greatest during the implementation of the project.

項目實施過程中的風險最大。
 

 

參考答案

1.答案:B,項目終止的原因包括目標實現了,目標消失了(不符合公司戰略),目標不可能實

現了(沒有資金了)

2.答案:C,執行過程組包含完成項目管理計劃中確定的工作以實現項目目標的一組過程。這個過程組不但要協調人員和資源,還要按照項目管理計劃整合并實施項目活動

3.答案:A,項目風險在初始階段最大.根據答案判斷,AB 兩個選項為相反選項,因此答案必定從 AB 中進行選擇,根據判斷,此題很容易得到答案 A